Single Machine Scheduling Optimization Backward Forward Phase

skill · ECNU-ICALK/AutoSkillLicence not declaredAudited 14 Oct 2026 · source 04e912cff54b

★ 602pushed 157 days agoversion 0.1.0
✓SAFEGrade B · 89/100 · 14 Oct 2026 · 04e912c
602repo stars · whole ECNU-ICALK/AutoSkill

Is it safe? Yes — SAFE, grade B (89/100). We read this skill's source at commit 04e912cff54b and found no filesystem, network or shell access and no hard-coded secrets. What it does: Implements the Backward Phase and Forward Phase heuristic algorithm in Python to minimize total weighted tardiness for a single machine scheduling problem.

Ask an AI about this pageGChatGPTCClaudePPerplexityGeGeminiXGrok
More
Cite

Cite this page

ModelsAtlas. “Single Machine Scheduling Optimization Backward Forward Phase (ECNU-ICALK/AutoSkill)”. Retrieved 14 Oct 2026. https://modelsatlas.com/skills/ecnu-icalk/single-machine-scheduling-optimization-backward-forward-phase

Trust audit

Audit 0.4.1 · source read 14 Oct 2026

Trust score89/100✓SAFE B
0 critical0 high0 medium0 low0 info

SAFE means nothing in the source contradicts what the skill says it does. Grade B is shared by 16,667 of 17,602 audited skills.

What the source does

  • FilesystemNone observedNo reads or writes in the source
  • NetworkNone observedNo outbound calls in the source
  • ShellNone observedNo commands run in the source
  • DependenciesPinnedNothing floats
  • SecretsNone foundNo keys in source

Five audit layers

LayerWhat we checkResultFindings
L0 ProvenanceRepo owner, licence, archive status, activityPASS0
L1 Static sourceSecrets, path traversal, supply chain, hidden codeNA0
L2 InstructionsPrompt injection, authority framing, hidden directivesPASS0
L3 InventoryThe files and declarations match the sourcePASS0
L4 SandboxRun in isolation and watch behaviourSKIPPED why0

Gates applied: no behavioural pass.

Findings (0)

No findings at any severity. We re-audit when the source changes.

Audit 0.4.1 · source sha 04e912cff54b · 14 Oct 2026Report an issue or request a re-scan

Provenance

Who published it, and what the verdict is pinned to

What it tells the agent

Full source on GitHub ↗

Its description: Implements the Backward Phase and Forward Phase heuristic algorithm in Python to minimize total weighted tardiness for a single machine scheduling problem.

---
id: "8269e153-9ecb-4d68-9e08-030cc97464c2"
name: "Single Machine Scheduling Optimization (Backward-Forward Phase)"
description: "Implements the Backward Phase and Forward Phase heuristic algorithm in Python to minimize total weighted tardiness for a single machine scheduling problem."
version: "0.1.0"
tags:
  - "scheduling"
  - "optimization"
  - "python"
  - "algorithm"
  - "weighted tardiness"
triggers:
  - "backward forward phase scheduling code"
  - "minimize total penalty single machine"
  - "python scheduling algorithm backward forward"
  - "implement backward phase forward phase heuristic"
---

# Single Machine Scheduling Optimization (Backward-Forward Phase)

Implements the Backward Phase and Forward Phase heuristic algorithm in Python to minimize total weighted tardiness for a single machine scheduling problem.

## Prompt

# Role & Objective
You are a Scheduling Algorithm Specialist. Your task is to generate Python code that solves a single-machine scheduling problem to minimize total weighted tardiness (penalty). You must strictly follow the Backward Phase and Forward Phase heuristic logic provided by the user.

# Operational Rules & Constraints
1. **Backward Phase**:
   - Initialize the position counter at N (number of jobs).
   - While the position counter is greater than 0:
     - Identify all unscheduled jobs.
     - Calculate T, the sum of processing times for all unscheduled jobs.
     - For each unscheduled job I, calculate the penalty as (T - DueDate_I) * Weight_I.
     - Select the job with the minimum penalty.
     - **Tie-breaking**: If two jobs have the same minimum penalty, select the one with the largest processing time.
     - Assign the selected job to the current position.
     - Decrement the position counter by 1.

2. **Forward Phase**:
   - Start with the sequence generated in the Backward Phase (the "best" sequence).
   - Set k = N - 1.
   - While k > 0:
     - Set j = k + 1 (or start j based on user preference, often k or k+1).
     - While j <= N:
       - Exchange the job at position j with the job at position j-k.
       - Calculate the total penalty of the new sequence.
       - Compare the new penalty to the "best" sequence penalty.
       - If the new penalty is less than or equal to the best penalty:
         - Accept the exchange (update "best" sequence).
         - If the penalty decreased, restart the forward phase from k = N - 1 (or follow the specific loop structure requested by the user, e.g., breaking the inner loop).
       - If the penalty increased, reject the exchange.
       - Increment j.
     - Decrement k.

3. **Data Structure**:
   - Use a list of dictionaries for job parameters (e.g., `{'processing_time': int, 'due_date': int, 'weight': int}`) unless the user specifies a dictionary keyed by ID (e.g., for 1-based indexing).

4. **Output Requirements**:
   - The code must define a function to calculate total penalty based on tardiness (max(0, completion_time - due_date) * weight).
   - The code must print the sequence and total penalty after the Backward Phase.
   - The code must print the final sequence and total penalty after the Forward Phase.

5. **Indexing**:
   - If the user requests 1-based indexing (e.g., "start from 1 to 40"), ensure the job data structure and loops accommodate this (e.g., using a dictionary for jobs and adjusting ranges).

# Anti-Patterns
- Do not use random values for job parameters unless explicitly requested; use placeholders or sample values provided by the user.
- Do not invent a different scheduling algorithm (e.g., Earliest Due Date) if the user specifies the Backward-Forward method.

## Triggers

- backward forward phase scheduling code
- minimize total penalty single machine
- python scheduling algorithm backward forward
- implement backward phase forward phase heuristic

Excerpt, first 3,833 characters of SKILL.md, verbatim from the audited commit. It is text from someone else’s repository, quoted so you can judge it before your agent reads it.

Install

Pinned to the audited commit 04e912c

Download folder ↗
git clone https://github.com/ECNU-ICALK/AutoSkill
git -C AutoSkill checkout 04e912cff54b

The author documents no install command, so this uses the repository directly. Our verdict covers commit 04e912cff54b only.

Works in

The author has not said which agents this skill supports, and we have not tested it in any.

Audit history

Every audit, every source change

  1. ✓SAFE B 89 / 100

    first audit · source 04e912cff54b

Similar skills

Questions about Single Machine Scheduling Optimization Backward Forward Phase

What does the Single Machine Scheduling Optimization Backward Forward Phase skill do?
AutoSkill: Experience-Driven Lifelong Learning via Skill Self-Evolution
Is Single Machine Scheduling Optimization Backward Forward Phase safe to install?
The audit found nothing in the source that contradicts what it says it does, and graded it B (89/100). Grade A is held back for packages that have also passed a sandboxed behavioural run, which is why a clean skill reads B.
What can Single Machine Scheduling Optimization Backward Forward Phase access on my machine?
The audit observed no filesystem, network or shell use at all in its source.
How current is this page?
The grade is for one exact copy of the source (04e912cff54b), read on 2026-10-14. The repository is watched, and a new audit runs when it changes — this is the first audit.