Agent skill · Audited from source
Production Scheduling
skill · LeoYeAI/openclaw-master-skillsMIT licenceAudited 8 Oct 2026 · source 4f3b4a2a472e
Is it safe? Yes — SAFE, grade B (89/100). We read this skill's source at commit 4f3b4a2a472e and found no filesystem, network or shell access and no hard-coded secrets. What it does: Codified expertise for production scheduling, job sequencing, line balancing, changeover optimisation, and bottleneck resolution in discrete and batch manufacturing. Informed by production schedulers with 15+ years…
Cite
Cite this page
ModelsAtlas. “Production Scheduling (LeoYeAI/openclaw-master-skills)”. Retrieved 8 Oct 2026. https://modelsatlas.com/skills/leoyeai/production-scheduling
2 skills are called “Production Scheduling”. You are viewing LeoYeAI/openclaw-master-skills.
- LeoYeAI/openclaw-master-skills★ 2.2k✓SAFE
- affaan-m/ECC★ 264k✓SAFE
Trust audit
Audit 0.4.1 · source read 8 Oct 2026
SAFE means nothing in the source contradicts what the skill says it does. Grade B is shared by 17,406 of 18,389 audited skills.
What the source does
- FilesystemNone observedNo reads or writes in the source
- NetworkNone observedNo outbound calls in the source
- ShellNone observedNo commands run in the source
- DependenciesPinnedNothing floats
- SecretsNone foundNo keys in source
Five audit layers
| Layer | What we check | Result | Findings |
|---|---|---|---|
L0 Provenance | Repo owner, licence, archive status, activity | PASS | 0 |
L1 Static source | Secrets, path traversal, supply chain, hidden code | WARN | 1 |
L2 Instructions | Prompt injection, authority framing, hidden directives | PASS | 1 |
L3 Inventory | The files and declarations match the source | PASS | 0 |
L4 Sandbox | Run in isolation and watch behaviour | SKIPPED why | 0 |
Gates applied: no behavioural pass.
Findings (2)
MEDIUMObfuscation / stealthobf.base64_blob · skills/compdf-conversion-cli/scripts/license.xml:9
<key>k5Ey9KFlkqpj+SDkUw+5ED9lTA3En/qUi0zdrydUCH3kMWTE3Eh65NXnFCaxlY2omY2JHnlEoK7Li7oOEvM7eG5VPdcO/sFlMfoCRdnLYdepJ+uLzYwOWR8W4yQVve/clxVFTVRL4DFleKInGdpAxIbHZT2yi4ADAMENls1N1XSLojRuqXePXDeAT/4Mv4TTx0s
- Why
- No further detail recorded for this rule.
- Fix
- —
LOWPrompt injectionprompt.authority_framing · SKILL.md:24
You are a senior production scheduler at a discrete and batch manufacturing facility operating 3–8 production lines with 50–300 direct-labour headcount per shift. You manage job sequencing, line balan
- Why
- No further detail recorded for this rule.
- Fix
- —
Audit 0.4.1 · source sha 4f3b4a2a472e · 8 Oct 2026Report an issue or request a re-scan
Provenance
Who published it, and what the verdict is pinned to
- PublisherLeoYeAI GitHub userOwner of the repository this skill is read from
- Source folderLeoYeAI/openclaw-master-skills/skills/production-schedulingThe exact folder we audited
- LicenceMITAs the repository states it
- Commit pinned for this verdict4f3b4a2a472eA new audit runs when the source changes
- Repository statusNot archivedLast push 80 days ago
- Sandboxed runNot runSkills are read, not executed; layer L4 is skipped
What it tells the agent
Full source on GitHub ↗Its description: Codified expertise for production scheduling, job sequencing, line balancing, changeover optimisation, and bottleneck resolution in discrete and batch manufacturing. Informed by production schedulers with 15+ years…
---
name: production-scheduling
description: >
Codified expertise for production scheduling, job sequencing, line balancing,
changeover optimisation, and bottleneck resolution in discrete and batch
manufacturing. Informed by production schedulers with 15+ years experience.
Includes TOC/drum-buffer-rope, SMED, OEE analysis, disruption response
frameworks, and ERP/MES interaction patterns. Use when scheduling production,
resolving bottlenecks, optimising changeovers, responding to disruptions,
or balancing manufacturing lines.
license: Apache-2.0
version: 1.0.0
homepage: https://github.com/evos-ai/evos-capabilities
metadata:
author: evos
clawdbot:
emoji: "🏭"
---
# Production Scheduling
## Role and Context
You are a senior production scheduler at a discrete and batch manufacturing facility operating 3–8 production lines with 50–300 direct-labour headcount per shift. You manage job sequencing, line balancing, changeover optimization, and disruption response across work centres that include machining, assembly, finishing, and packaging. Your systems include an ERP (SAP PP, Oracle Manufacturing, or Epicor), a finite-capacity scheduling tool (Preactor, PlanetTogether, or Opcenter APS), an MES for shop floor execution and real-time reporting, and a CMMS for maintenance coordination. You sit between production management (which owns output targets and headcount), planning (which releases work orders from MRP), quality (which gates product release), and maintenance (which owns equipment availability). Your job is to translate a set of work orders with due dates, routings, and BOMs into a minute-by-minute execution sequence that maximises throughput at the constraint while meeting customer delivery commitments, labour rules, and quality requirements.
## Core Knowledge
### Scheduling Fundamentals
**Forward vs. backward scheduling:** Forward scheduling starts from material availability date and schedules operations sequentially to find the earliest completion date. Backward scheduling starts from the customer due date and works backward to find the latest permissible start date. In practice, use backward scheduling as the default to preserve flexibility and minimise WIP, then switch to forward scheduling when the backward pass reveals that the latest start date is already in the past — that work order is already late-starting and needs to be expedited from today forward.
**Finite vs. infinite capacity:** MRP runs infinite-capacity planning — it assumes every work centre has unlimited capacity and flags overloads for the scheduler to resolve manually. Finite-capacity scheduling (FCS) respects actual resource availability: machine count, shift patterns, maintenance windows, and tooling constraints. Never trust an MRP-generated schedule as executable without running it through finite-capacity logic. MRP tells you *what* needs to be made; FCS tells you *when* it can actually be made.
**Drum-Buffer-Rope (DBR) and Theory of Constraints:** The drum is the constraint resource — the work centre with the least excess capacity relative to demand. The buffer is a time buffer (not inventory buffer) protecting the constraint from upstream starvation. The rope is the release mechanism that limits new work into the system to the constraint's processing rate. Identify the constraint by comparing load hours to available hours per work centre; the one with the highest utilisation ratio (>85%) is your drum. Subordinate every other scheduling decision to keeping the drum fed and running. A minute lost at the constraint is a minute lost for the entire plant; a minute lost at a non-constraint costs nothing if buffer time absorbs it.
**JIT sequencing:** In mixed-model assembly environments, level the production sequence to minimise variation in component consumption rates. Use heijunka logic: if you produce models A, B, and C in a 3:2:1 ratio per shift, the ideal sequence is A-B-A-C-A-B, not AAA-BB-C. Levelled sequencing smooths upstream demand, reduces component safety stock, and prevents the "end-of-shift crunch" where the hardest jobs get pushed to the last hour.
**Where MRP breaks down:** MRP assumes fixed lead times, infinite capacity, and perfect BOM accuracy. It fails when (a) lead times are queue-dependent and compress under light load or expand under heavy load, (b) multiple work orders compete for the same constrained resource, (c) setup times are sequence-dependent, or (d) yield losses create variable output from fixed input. Schedulers must compensate for all four.
### Changeover Optimisation
**SMED methodology (Single-Minute Exchange of Die):** Shigeo Shingo's framework divides setup activities into external (can be done while the machine is still running the previous job) and internal (must be done with the machine stopped). Phase 1: document the current setup and classify every element as internal or external. Phase 2: convert internal elements to external wherever possible (pre-staging tools, pre-heating moulds, pre-mixing materials). Phase 3: streamline remaining internal elements (quick-release clamps, standardised die heights, colour-coded connections). Phase 4: eliminate adjustments through poka-yoke and first-piece verification jigs. Typical results: 40–60% setup time reduction from Phase 1–2 alone.
**Colour/size sequencing:** In painting, coating, printing, and textile operations, sequence jobs from light to dark, small to large, or simple to complex to minimise cleaning between runs. A light-to-dark paint sequence might need only a 5-minute flush; dark-to-light requires a 30-minute full-purge. Capture these sequence-dependent setup times in a setup matrix and feed it to the scheduling algorithm.
**Campaign vs. mixed-model scheduling:** Campaign scheduling groups all jobs of the same product family into a single run, minimising total changeovers but increasing WIP and lead times. Mixed-model scheduling interleaves products to reduce lead times and WIP but incurs moreExcerpt, first 6,001 characters of SKILL.md, verbatim from the audited commit. It is text from someone else’s repository, quoted so you can judge it before your agent reads it.
Install
Pinned to the audited commit 4f3b4a2
git clone https://github.com/LeoYeAI/openclaw-master-skills git -C openclaw-master-skills checkout 4f3b4a2a472e
The author documents no install command, so this uses the repository directly. Our verdict covers commit 4f3b4a2a472e only.
Works in which agents?
What its own text says, not a test
| Agent | Status | More |
|---|---|---|
| OpenClaw | Mentioned in its text, not tested | Skills for OpenClaw · About OpenClaw |
Audit history
Every audit, every source change
- ✓SAFE B 89 / 100
first audit · source
4f3b4a2a472e
README badge
For maintainers · shows the latest audit
[](https://modelsatlas.com/skills/leoyeai/production-scheduling/)
The badge shows our verdict and grade for this skill, and links back to this page. It changes when the audit does.
Similar skills
LeoYeAI/openclaw-master-skills
Run tests on BrowserStack. Use when user mentions "browserstack", "cross-browser", "cloud testing", "browser matrix", "test on safari", "test on firefox", or "browser compatibility".
LeoYeAI/openclaw-master-skills
Analyze test coverage gaps. Use when user says "test coverage", "what's not tested", "coverage gaps", "missing tests", "coverage report", or "what needs testing".
LeoYeAI/openclaw-master-skills
Generate Playwright tests. Use when user says "write tests", "generate tests", "add tests for", "test this component", "e2e test", "create test for", "test this page", or "test this feature".
LeoYeAI/openclaw-master-skills
Set up Playwright in a project. Use when user says "set up playwright", "add e2e tests", "configure playwright", "testing setup", "init playwright", or "add test infrastructure".
LeoYeAI/openclaw-master-skills
Use this skill whenever the user wants to do anything with PDF files. This includes reading or extracting text/tables from PDFs, combining or merging multiple PDFs into one, splitting PDFs apart, rotating pages, adding…
LeoYeAI/openclaw-master-skills
PDF conversion toolkit featuring AI layout analysis and OCR. Converts PDFs to Word, Markdown, JSON, PPT, CSV, HTML, and XML for seamless LLM data processing.
Add this badge to your README
[](https://modelsatlas.com/skills/leoyeai/production-scheduling/)
<a href="https://modelsatlas.com/skills/leoyeai/production-scheduling/"><img src="https://modelsatlas.com/skills/leoyeai/production-scheduling/badge.svg" alt="ModelsAtlas: SAFE B"></a>
Questions about Production Scheduling
What does the Production Scheduling skill do?
Is Production Scheduling safe to install?
What can Production Scheduling access on my machine?
Which assistants does Production Scheduling work with?
How current is this page?
Sources
- github.com/LeoYeAI/openclaw-master-skills/tree/main/skills/produ — the audited source at commit 4f3b4a2a472e and every finding aboveObserved · 8 Oct 2026
Spotted something wrong? Report a correction · Methodology
Keep going in your AI
Opens with this page as the source. We add nothing else to the prompt.
- What does the Production Scheduling skill do?
- Is Production Scheduling safe to install?
- What can Production Scheduling access on my machine?